Ala
Moana Hotel
Honolulu, Hawaii The
construction utilized special precast concrete "column
tree" frames supporting precast slabs. Dr. Yee's
patented NMB Splice Sleeve mechanical couplers were
used to join the "column trees" together to
develop a monolithic structure. This system allowed
crews to erect one complete 1684 square meter (18,120
sq. ft.) floor every 2 1/2 days. The hotel consists
of a 38-story tower with 960 rooms and a 13-story wing
with 308 rooms.
View
More Photos
View Articles:
|
|
|
| |
Dalian
Xiwang Building
Dalian, China 43-story
precast concrete office building utilizing precast concrete
beams, slabs and exterior architectural cladding designed
for high seismic activity. Precast concrete construction
progressed at a rate of one floor every three days.
View
More Photos
|
|
|
| |
Kahala
Mandarin Oriental Hotel
Honolulu, Hawaii An
11-story luxury hotel with over 350 rooms utilizing
precast joists, beams, wall panels, balcony slabs and
double tees. Slender precast columns and beams create
the eye-catching exterior facade trellis system.
View
More Photos
|
|
|
| |
Honolulu
Municipal Office Building
Honolulu, Hawaii A
15-story prestressed concrete building boasting 12,700
square meters of column-free space. Long span (20 to
24 meters) precast, prestressed floor joists supported
by hollow post-tensioned in situ girders constitute
the basic framing system for each floor. |
|
|
| |
Ramon
Magsaysay Building
Manila, Philippines An
18-story, 15,540 square meter office building with composite
precast, prestressed concrete floor frame designed for
Seismic Zone 3 forces. |
|
|
| |
Hotel
Leopalace
Guam A
22-story hotel tower with structural steel frame and
precast concrete balconies, walls and facade. As part
of this project, a value engineered 6-story parking
garage constructed with precast, prestressed composite
elements resulted in substantial savings in time, labor
and construction cost.
View
More Photos
|
|
|
|
|
|
| |
Millennium
Hilton Hotel
New York, New York A
57-story hotel utilizing reinforced concrete that was
located immediately across the WTC complex. Inspection
and evaluation of the structural condition after the
WTC attacks was provided. The exterior facade was severely
damaged and a structural investigation report was prepared
based on field observations and mathematical analyses
to verify the structural integrity of the building. |
|
|
| |
Hong
Kong Bank
Jakarta, Indonesia
The
first structural high-rise precast concrete building
in Indonesia. All beams, slab soffits, and exterior
column claddings were constructed of precast concrete
and tied together with an in-situ reinforced concrete
topping to integrate all precast elements into a monolithic
structural frame. The building was designed for seismic
conditions required for the region.
|
|